Construction of the Des Cultures Wind Farm Begins
As announced at our open house event on August 18 and 19, construction of the Des Cultures Wind Farm will begin the first week of September. . The work scheduled for this fall includes the construction of access roads, as well as excavation and pouring of the foundations for the six future turbines. Visit http://www.ksenergies.ca for regular construction updates.
Week of November 2, 2020
SAINT-MICHEL
Construction of the work area for installation of the met tower.
Installation of piles for the foundation of turbines T4 and T6.
SAINT-RÉMI
Construction of the temporary access road between turbines T1 and T2 and installation of culverts.
Steel rebar installation for the foundation of turbine T1.
Installation of the concrete slab of the foundation of turbine T3 and installation of the anchor cage.
Week of November 9, 2020
SAINT-MICHEL
Construction of the work area for installation of the met tower.
Installation of piles at turbine T4.
Installation of piles at turbine T5.
Steel rebar installation and pouring of concrete for piles at turbine T6.
SAINT-RÉMI
Installation of formwork for the foundation of turbine T1.
Concrete pour for the foundation of turbine T1. Week of November 16, 2020
SAINT-MICHEL
Completion of access road of turbines T4, T5 and T6.
Installation of piles for the foundation of turbine T5.
Steel rebar installation and pouring of concrete for piles at turbines T4 and T6.
Installation of the concrete slab of the foundation of turbine T4 and installation of the anchor cage.
SAINT-RÉMI
Pouring of concrete for the foundation of turbine T1 and removing of formwork.
Steel rebar installation for the foundation of turbines T2 and T3.
Week of November 23, 2020
SAINT-MICHEL
Installation of piles for the met tower.
Steel rebar installation for the foundation of turbine T4.
Steel rebar installation and pouring of concrete for piles for turbine T5 and for the met tower.
Installation of the concrete slab of the foundation of turbines T5 and T6.
Installation of the anchor cage of turbine T6 and of the steel rebar.
SAINT-RÉMI
Backfilling of the foundation of turbine T1 and completion of the work area.
Pouring of concrete for the foundation of turbine T2 and removing of formwork.
Steel rebar installation for the foundation of turbine T3 and formwork installation.
Week of November 30, 2020
SAINT-MICHEL
Removal of formwork for the piles for the met tower, backfilling, grounding and preassembly of tower.
Installation of formwork and pouring of concrete for the foundation of turbine T4.
Steel rebar installation for the foundation of turbines T5 and T6.
SAINT-RÉMI
Completion of work area of turbine T2.
Backfilling and grounding of the foundation of turbine T2.
Pouring of concrete for the foundation of turbine T3 and removal of formwork.
Week of November 30, 2020
SAINT-MICHEL
- Pouring of concrete for the foundation slab of turbine T5
- Steel rebar installation for the foundation of turbines T4, T5 and T6
- Installation of formwork and pouring of concrete for the foundation of turbine T4
SAINT-RÉMI
- Completion of work area of turbine T2
- Pouring of concrete for the foundation of turbine T3 and removal of formwork
- Backfilling and grounding of the foundation of turbine T2
- Removal of formwork for the piles for the met tower, backfilling, grounding and preassembly of tower
Week of December 7, 2020
SAINT-MICHEL
- Completion of work area of turbine T4
- Installation of steel rebar and formwork for the foundation of turbine T5
- Pouring of concrete for the foundation of turbines T5 and T6
- Removing formwork of the foundation of turbine T6
- Backfilling and grounding of the foundation of turbine T4
SAINT-RÉMI
- Completion of work area of turbine T3
- Backfilling and grounding of the foundation of turbine T3
- Preassembly of meteorological tower
Week of December 14, 2020
SAINT-MICHEL
- Pouring of concrete for the foundation of turbine T5 and removal of formwork.
- Backfilling of the foundation of turbines T5 and T6 and grounding.
- Completion of the work area of turbines T4, T5 and T6.
SAINT-RÉMI
- Installation of the meteorological tower.
Week of December 21, 2020
SAINT-MICHEL
- Construction work completed for the season.
SAINT-RÉMI
- Construction work completed for the season.