Kahnawà:ke’s Economic Development Commission

BLOG POSTS

Des Cultures Wind Farm Construction Schedule – Virtual Public Meeting – Tuesday, May 4th at 7 pm.
May 4, 2020

 

Virtual Public Meeting on Tuesday May 4th at 7 p.m.
On Tuesday May 4th, at 7 p.m., we will be holding a virtual public information meeting in order to present the 2021 construction schedule of the Des Cultures Wind Project.

To register, go to
projeteoliendescultures.com/en/meeting and fill out the online form. The event will be held in French but questions in English will be answered accordingly.

Our team is available to answer your questions.
Please reach out to us at 1 844-668-6818 or info@projeteoliendescultures.com.

_____________________________________________________________________________________

Des Cultures Wind Farm

As announced at our open house event on August 18 and 19, construction of the Des Cultures Wind Farm will begin the first week of September. The work scheduled for this fall includes the construction of access roads, as well as excavation and pouring of the foundations for the six future turbines.  Visit http://www.ksenergies.ca for regular construction updates.

Week of November 2, 2020
SAINT-MICHEL

Construction of the work area for installation of the met tower.
Installation of piles at turbine T4.
Installation of piles at turbine T5.
Steel rebar installation and pouring of concrete for piles at turbine T6.

SAINT-RÉMI

Installation of formwork for the foundation of turbine T1.
Concrete pour for the foundation of turbine T1.

Week of November 16, 2020
SAINT-MICHEL

Completion of access road of turbines T4, T5 and T6.
Installation of piles for the foundation of turbine T5.
Steel rebar installation and pouring of concrete for piles at turbines T4 and T6.
Installation of the concrete slab of the foundation of turbine T4 and installation of the anchor cage

SAINT-RÉMI
Pouring of concrete for the foundation of turbine T1 and removing of formwork.
Steel rebar installation for the foundation of turbines T2 and T3.

Week of November 23, 2020
SAINT-MICHEL

Installation of piles for the met tower.
Steel rebar installation for the foundation of turbine T4.
Steel rebar installation and pouring of concrete for piles for turbine T5 and for the met tower.
Installation of the concrete slab of the foundation of turbines T5 and T6.
Installation of the anchor cage of turbine T6 and of the steel rebar.

SAINT-RÉMI
Backfilling of the foundation of turbine T1 and completion of the work area.
Pouring of concrete for the foundation of turbine T2 and removing of formwork.
Steel rebar installation for the foundation of turbine T3 and formwork installation.

See more construction updates click here:   www.projeteoliendescultures.com

 

Click Here for a brief overview of construction activities planned for the next two weeks in the municipalities of Saint-Michel
and Saint-Rémi.